CEBAF  Newport News, VA

Customer: U.S. Department of Energy

The Continuous Electron Beam Accelerator Facility, now known as the Jefferson Laboratory, involved construction of an underground closed loop tunnel with ancillary buildings for a linear accelerator.  Encompassed excavation of an open trench to construct approximately 4,600 LF of 10 ft. x 13.5 ft. rectangular concrete tunnel.  Caddell also completed construction of 16 steel-framed single-story structures ranging in size from 210 SF to 13,000 SF.  Project also included construction of the machine control center; a computer room with raised flooring; two access buildings; and a low-conductivity water system, cooling towers, heat exchangers, D.C. power equipment, toilet facilities and bridge crane.  $20.6M